Warning: fopen(/home/virtual/kwjs/journal/upload/ip_log/ip_log_2024-03.txt): failed to open stream: Permission denied in /home/virtual/lib/view_data.php on line 88 Warning: fwrite() expects parameter 1 to be resource, boolean given in /home/virtual/lib/view_data.php on line 89 Optimization of Robot Welding Process of Subassembly Using Genetic Algorithm in the Shipbuilding

Journal of KWJS 2009;27(2):57-62.
Published online May 18, 2009.
유전자 알고리즘을 이용한 조선 소조립 로봇용접공정의 최적화
, ,
 
Optimization of Robot Welding Process of Subassembly Using Genetic Algorithm in the Shipbuilding
Ju-Yong Park, Jeong-Jin Seo, Hyun-Jin Kang
Abstract
  This research was carried out to improve the productivity in the subassembly process of shipbuilding through optimal work planning for the shortest work time. The work time consist of welding time, moving time of gantry, teaching time of robot and robot motion time. The shortest work time is accomplished by even distribution of work and the shortest welding sequence. Even distribution of work was done by appling the simple algorithm. The shortest work sequence was determined by using GA. The optimal work planning decreased the total work time of the subassembly process by 4.1%. The result showed the effectiveness of the suggested simple algorithm for even distribution of work and GA for the shortest welding sequence.
Key Words: Shipbuilding, Assembly, Genetic algorithm, Even distribution of work, Shortest weldingsequence


ABOUT
BROWSE ARTICLES
ARTICLE CATEGORY 
FOR CONTRIBUTORS
Editorial Office
#304, San-Jeong Building, 23, Gukhoe-daero 66-gil, Yeongdeungpo-gu, Seoul 07237, Korea
Tel: +82-2-538-6511    Fax: +82-2-538-6510    E-mail: koweld@kwjs.or.kr                

Copyright © 2024 by The Korean Welding and Joining Society.

Developed in M2PI